Task:
The table below includes a set of activities (tasks), durations and dependencies. Create a Gantt chart using Microsoft Project for this set of tasks – except put “Yourlastname Finishes Up” (substituting your real last name) in place of T16. Print the Gantt chart and the associated activity network (try not to use too much paper). Identify the critical path (list tasks involved in it), and the expected completion date.
Suppose that a serious, unanticipated setback occurs and instead of taking 4 days, task T4 takes 10 days. Revise your project schedule. Identify the new critical path (list tasks involved in it). How much is the project completion expected to be delayed as a result of this 6 day setback?
Task |
Duration (days) |
Dependencies |
T1 |
2 |
|
T2 |
3 |
T1 |
T3 |
2 |
T1,T2 |
T4 |
4 |
|
T5 |
2 |
|
T6 |
3 |
T3,T4 |
T7 |
4 |
T3 |
T8 |
7 |
T7 |
T9 |
3 |
T6 |
T10 |
1 |
T5,T9 |
T11 |
2 |
T9 |
T12 |
4 |
T10 |
T13 |
7 |
T3,T4 |
T14 |
2 |
T8,T9 |
T15 |
4 |
T12,T14 |
T16 |
2 |
T15 |
Hand in:
1) Gantt and Network printouts.
2) Answers to all questions above.